August 2019

“AL MUSTAFA ORPHANAGE” -PROBLEMS FACED DURING INSTALLATION OF SOLAR PANELS Interns: SAAD SHAKIL        HASSAAN QADEER        UROOJ FATIMA PROJECT TITLE: Installation of 12.35kW Solar Power Plant PROBLEM STATEMENT: Technical/Civil problems faced at the time of installation DESCRIPTION: The key problems that

July 2019

Load Transition in Hospital INTRODUCTION: Before the installation of PV-System at Bilquis-Mushaf Hospital, in beginning months of 2017, it’s detailed planning and Data collection was taken off.  Load calculation and estimation was a very crucial part of this analysis and

June 2019

INSTALLATION AND COMMISSIONING AT RASHIDABAD PROJECT IOTAWATT: ➢ Problem statement: OpticsRE has huge gaps recently which is probably due to internet outage and which results in data loss. ➢ Solution: In case of an internet outage, IotaWatt is programmed to

June 2019

ORPHANAGE SOLAR POWER PROJECT PROJECT TITLE: Eminent and cost effective solar power project. PROBLEM STATEMENT: Compare the Received RFQs from different vendors Introduction Al- Mustafa Orphanage Solar project’s team made RFQ based on the data collected through IOTAWATT (Energy Monitoring

July 2018

Contents Water Generator Project Orphanage Solar Project Home Solar Project Hospital Solar Project Water Filter Project Water Generator Project Update De-Humidifier condensation data  The graph highlights the condensation rates, in liters, of the de-humidifier, when operated at different weather conditions

Mar 2018

Contents Water Generator Project Orphanage Solar Project Home Solar Project Hospital Solar Project Water Filter Project Water Generator Project Update Scope and Requirements The objective of this project is to provide water for drinking and cooking in places where access to

Apr 2018

Contents Orphanage Solar Project Home Solar Project Water Generator Project Hospital Solar Project Water Filter Project Orphanage Solar Project Update Scope and Requirements In order to properly size the solar power system for the orphanage project, it is very important to

Jun 2018

Contents Water Generator Project Home Solar Project Hospital Solar Project Orphanage Solar Project Water Filter Project Water Generator Project Update Scope Assess the performance of the water generator using solar power. A Belin 30 liter dehumidifier imported from China directly from

May 2018

Contents Water Generator Project Home Solar Project Hospital Solar Project Orphanage Solar Project Water Filter Project Water Generator Project Update Scope The team validated the performance of the solar panels used to operate the dehumidifier. Three solar panels of 150W each